Engineering, Procurement & Construction of Coal Domes (2 set x Φ120m) and relevant stacking-reclaiming equipment
Location: Nanjing, China
Scope of Work: Coal Domes & relevant stacking-reclaiming equipment
Status: Completed
-
Engineering, Procurement & Construction of Coal Conveyor System, including conveyor and relevant devices, transfer tower, galleries and all the relevant embedment works, mechanical works, E&I, Grounding, Lighting, Fabrication, QAQC, Transportation, Installation, Test Running, O&M Training, Warranty etc..
Location: Haikou, China
Scope of Work: Completed
Status: Coal Handling System
-
Engineering, Procurement & Construction of Coal Handling & Storage System starting from the conveyor underneath the ship unloader until to boiler coal bunker, including 2 sets of Φ120M coal domes & relevant stacker-reclaimer, conveyor and relevant devices, transfer tower, galleries and all the relevant embedment works, mechanical works, E&I, Broadcasting, MCC, Grounding, Lighting, Fabrication, QAQC, Transportation, Installation, Test Running, O&M Training, Warranty etc..
Location: Fujian, China
Scope of Work: Coal Handling & Storage System
Status: Completed
-
Engineering, Procurement & Construction of Coal Domes (Φ90m) and relevant stacking-reclaiming equipment (stacking capacity: 600t/h, reclaiming capacity:300t/h)
Location: Jiangsu, China
Scope of Work: Coal Domes & relevant stacking-reclaiming equipment
Status: Completed
-
First EPC project. Starting from Conveyors at Truck Unloading Station until to boiler coal bunker, including Turbine Room Steel Structure, 18 lines of coal conveyors and devices, indoor coal yard, transfer towers and galleries, and and all the relevant embedment works, mechanical works, E&I, Broadcasting, MCC, Grounding, Lighting, Fabrication, QAQC, Transportation, Installation, Test Running, O&M Training, Warranty etc..
Location: Zhejiang, China
Scope of Work: Turbine Room and Coal Storage & Handling System
Status: Completed