Project Location: Masinloc, Philippines
Client: San Miguel Corporation
Scope of Work: On-site prefabrication and installation of gas and air ducts for #4/#5 supercritical boilers (984T/H x 2 units) of the power plant, including the construction of a temporary on-site prefabrication workshop and the prefabrication and installation of air and flue gas ducts and support platforms.
Project Location: Masinloc, Philippines
Client: San Miguel Corporation
Scope of Work: Installation of Boiler Auxiliaries and turbine generator equipment for power plant units #4/#5, including the installation of turbines, generators, condensers, and their auxiliary equipment, as well as the installation of all plant auxiliary equipment, miscellaneous pumps, embedded parts, and other mechanical equipment.