Project Location: Masinloc, Philippines
Client: San Miguel Corporation
Scope of Work: On-site installation of boiler pressure parts and auxiliary equipment, including the installation of main steam pipes and boiler steel structures.
Project Location: Masinloc, Philippines
Client: San Miguel Corporation
Scope of Work: On-site prefabrication and installation of gas and air ducts for #4/#5 supercritical boilers (984T/H x 2 units) of the power plant, including the construction of a temporary on-site prefabrication workshop and the prefabrication and installation of air and flue gas ducts and support platforms.
Project Location: Masinloc, Philippines
Client: San Miguel Corporation
Scope of Work: Installation of Boiler Auxiliaries and turbine generator equipment for power plant units #4/#5, including the installation of turbines, generators, condensers, and their auxiliary equipment, as well as the installation of all plant auxiliary equipment, miscellaneous pumps, embedded parts, and other mechanical equipment.
Project Location: Masinloc, Philippines
Client: SMC Global Power
Scope of Work: Prefabrication, installation and pressure test of piping for supercritical boiler power plants.